Wednesday, March 11, 2009

Pityriasis Rosea Bilder

Photos of the process







Hello,
here are a few pictures of what has been done so far, you can see when we started to dismantle the roof, and you can see the change that has been given the house general.

rasillón Above the roof put a layer of hydraulic lime mortar, waterproof sheet over Proctor directly above it and the tile.

(If you want to see more size photos click on them)
health.





















(before and during change roof eaves)

Thursday, March 5, 2009

Yellow Blisters Back Of Throat

Today ... March 1909

Hello!
4 puffs of air, a couple of storms, tears, sweat, laughter, great crisis, hard work and little money .... and spend more than 6 months!

Well how will we tell you the house today,

we removed the old plaster replace it with one based on all kinds .... Probatino a piece with a cast of Albarracín (thanks to Bird, DEP, a mason who was going to do the task fat and left without saying goodbye at the end August) another piece mixed with lime mortar (CL90S) sand and white cement, plaster another common .... and so we moved forward.

lift the entire soil, rubble removal ....

And we start with the roof and roof
everything was new, with wooden beams Pino Soria (Durga treated products), rasillón, waterproof and breathable film Frameshield of PriMateria Proctor (www.primateria.net Aupa Iñaki! ) and Arabic tiles Alagón artisan.
Install 2 Velux type roof windows, one on each roof water. Lack

put insulation between the joists, which will be of hemp (www.aisleco.com)

We have materials to continue (We already have the floor tiles of clay, the same artisan who has made the tiles), we Cupolex floor ... etc

But now we have the work stopped, hopefully not for long, we deciding where to go ... we're assessing what type of heating to ... but yes, we have started the house from the roof and has been on the wafer. While that going to live this summer of 2009 that was what we wanted to see it increasingly difficult .....

Health and re-evolution!